This post was originally published on here
The Searcy School District is “looking at starting” on its new animal science building by May 1, according to Assistant Superintendent Dean Stanley.
Stanley told the Searcy School Board that the second set of drawings from architects from Modus Studios out of Fayetteville will be submitted to the construction managers by Jan. 15, and “from that point, in 30 days it has to go to the facilities department [on the state level] to re-review. At that point, it’s like a three-week period of advertising for the bid process. Best-case scenario looks like the next set of bids would come out in mid-March, which would take us through probably the mid to the end of April when the first shovel of dirt would be turned.”